POS V2 — Build Progress

Phase 1: Foundation — March 17, 2026

11
Tasks Done
0
In Progress
2
Remaining
204
Tests Passing
Phase 1: Foundation (Weeks 1-3) In Progress
Phase 2: Core Modules (Weeks 4-7) Pending

Activity Log

[04:02] [PASS] HQ Server — 19 tests (1 health + 18 auth)
[04:00] [BUILD] Auth module — login, JWT (Jose), RBAC, permission guard, Argon2
[03:58] [FIX] Drizzle version mismatch (0.38 → 0.39) in servers
[03:55] [BUILD] HQ Server + Store Server — Fastify skeletons, health checks
[03:55] [BUILD] @pos/db-schema — 38+ tables, ALL domains
[03:50] [PASS] @pos/event-bus 22 | @pos/tax-engine 21
[03:46] [PASS] @pos/backend-adapter 36 | @pos/sync-protocol 13 | @pos/i18n 8
[03:42] [PASS] @pos/rule-engine 26 | @pos/shared-types 58
[03:35] [DONE] Monorepo setup complete
[03:30] [START] Phase 1: Foundation